Phases of Execution

The design and construction of the Uotila Wooden School and Day-Care Centre is provisionally planned to take place between 2023 and 2026 as follows:

  • Procurement 4–11/2023
  • Development phase 12/2023–2/2024
  • Construction phase 3/2024–12/2025
  • Commissioning 12/2025

The City of Rauma will put the design and implementation of the project up for bidding through a negotiation process. The project will be implemented as a turnkey contract. In a turnkey project, the contractor is responsible for the design and implementation of the entire construction project.

Decision History

  • The decision to build the school and day-care centre as a wooden building was made by the council in 2019.
  • The needs assessment was completed in late 2021.
  • The project plan was completed in late 2022.
  • The project plan was approved by the City Board in spring 2023.

According to the decision of the Rauma City Board of 6 February 2023, the City of Rauma will allocate 24.3 million euros for the implementation of the project based on the approved project plan.